J
jp
Hi,
I have ms project 2003 and there are various tasks but I'll take one to show
example:
Task1a really takes only 30 minutes to accomplish.
However, the policy is that request take at least 3 days to complete.
That's because it has to go to the Change Request Board and documentation
etc...
so it may take 3 days or possibly 4. What is the best way to set up this
task in ms Project knowing that it could be done in 30 mins but because of
policies and procedures it takes 3 to 4 days.
Thanks in advance.
-jp
I have ms project 2003 and there are various tasks but I'll take one to show
example:
Task1a really takes only 30 minutes to accomplish.
However, the policy is that request take at least 3 days to complete.
That's because it has to go to the Change Request Board and documentation
etc...
so it may take 3 days or possibly 4. What is the best way to set up this
task in ms Project knowing that it could be done in 30 mins but because of
policies and procedures it takes 3 to 4 days.
Thanks in advance.
-jp