I am using Project Server 2007.
I log in to PWA as an administrator - go to My Works > My Tasks -
select a task for a project I created (so I am the owner of the
project) - select reassign task - on the task reassignment page,
select a different resource and click Submit - I get a message that
"The selected task(s) could not be reassigned due to the following
reason(s): Access Denied".
Since I am an administrator, I have the reassign task permission (and
all other possible permissions), so why am I getting this error?
Also when I select the project and click the option to "create task
under this project", on the "New Task" page, the project pull-down is
not populated with the selected project's name and the selected
project is not available in the pull-down. Wondering if I am missing
something...
Thank you for any help you can provide!
I log in to PWA as an administrator - go to My Works > My Tasks -
select a task for a project I created (so I am the owner of the
project) - select reassign task - on the task reassignment page,
select a different resource and click Submit - I get a message that
"The selected task(s) could not be reassigned due to the following
reason(s): Access Denied".
Since I am an administrator, I have the reassign task permission (and
all other possible permissions), so why am I getting this error?
Also when I select the project and click the option to "create task
under this project", on the "New Task" page, the project pull-down is
not populated with the selected project's name and the selected
project is not available in the pull-down. Wondering if I am missing
something...
Thank you for any help you can provide!