J
jlh83
In Project and PWA tasks assigned to (dual) resources are showing 100%
completed but the resources continue to receive email notifications stating
the tasks need progress updates. When looking at individual resource hours
remaining work is still showing even though the task completion is showing
100%.
IE...
Under RESOURCES / Adjust Actual / Individual Person for a project shows:
Work = 8 hrs, Remaining Work = 8 hrs, % Work Complete = 0
Under PROJECTS / Individual Project shows
All tasks as 100% complete
I'm having a hard time understanding why the tasks are showing 100% complete
in one place and remaining work in another. How can I fix this so the
resource no longer recieves the email notifications? Help!
completed but the resources continue to receive email notifications stating
the tasks need progress updates. When looking at individual resource hours
remaining work is still showing even though the task completion is showing
100%.
IE...
Under RESOURCES / Adjust Actual / Individual Person for a project shows:
Work = 8 hrs, Remaining Work = 8 hrs, % Work Complete = 0
Under PROJECTS / Individual Project shows
All tasks as 100% complete
I'm having a hard time understanding why the tasks are showing 100% complete
in one place and remaining work in another. How can I fix this so the
resource no longer recieves the email notifications? Help!