S
Stacy
I have 2 databases, one for the open projects and one for the closed/archived
projects. Resources are still getting task reminders even though the project
has been closed out. In the project remaining work has been set to 0, and
100% complete. I have not been able to resolve this problem, I have run a
qurey in the database and in the past it has worked. It is not clearing.
Any ideas??
Thanks,
Stacy
projects. Resources are still getting task reminders even though the project
has been closed out. In the project remaining work has been set to 0, and
100% complete. I have not been able to resolve this problem, I have run a
qurey in the database and in the past it has worked. It is not clearing.
Any ideas??
Thanks,
Stacy