D
Daniel Lowicki
Hi .. this is about the task list. I have two tasks. One ends well before
the next one starts.
What I want to do is add another task inbetween to mark this delay. So I
need a task that starts after the first and ends before the second task. The
delay in days should be calculated.
E.g (ddmmyyyy).
Task1, 5d, Start: 1.1.2008, End: 5.1.2008
DELAY, 4d, Start: 6.1.2008, End: 9.1.2008 <-- This should line should
change if task 1 or 2 change!
Task2, 5d, Start: 10.1.2008, End: 15.1.2008
Is this possible?
br
Daniel
the next one starts.
What I want to do is add another task inbetween to mark this delay. So I
need a task that starts after the first and ends before the second task. The
delay in days should be calculated.
E.g (ddmmyyyy).
Task1, 5d, Start: 1.1.2008, End: 5.1.2008
DELAY, 4d, Start: 6.1.2008, End: 9.1.2008 <-- This should line should
change if task 1 or 2 change!
Task2, 5d, Start: 10.1.2008, End: 15.1.2008
Is this possible?
br
Daniel