R
Rich
I have a task that takes 40 hours to complete. I asssign 3 people to
it. Two work full time and 1 works part time(3 hours per day during
the week and 8 on the weekends). If I set the resource allocation
for 100% for all users project takes the 40 hours and gives each
person 13.33 hours of work to do causing the task to take longer then
needed as the part time user takes more days to complete his 13.33
hours.
I would like to be able to
1. Have it allocate the resources based on getting the task done in
the least amount of calandar days rather then giving each person the
same amount of work. The guy that works 8 hours per day should just
keep working on the task until it is done.
Is this possible? I tried resource leveling which I thought might help
but it didnt seem to have any luck. The speciality employee also
charges more per hour if that can help microsoft project to figure out
resource allocation.
I posted a similar inquiry a while back and got a response from one
person who thought this was not possible. I think he might be right
but I don't understand why project can't handle that allocation. I
can manually edit the working hours the week of that task (once I know
when the task is starting) but I cant seem to do much else.
Until I get to the task in my schedule it shows that it will take way
longer then it really does. Any ideas on how I can fix
it. Two work full time and 1 works part time(3 hours per day during
the week and 8 on the weekends). If I set the resource allocation
for 100% for all users project takes the 40 hours and gives each
person 13.33 hours of work to do causing the task to take longer then
needed as the part time user takes more days to complete his 13.33
hours.
I would like to be able to
1. Have it allocate the resources based on getting the task done in
the least amount of calandar days rather then giving each person the
same amount of work. The guy that works 8 hours per day should just
keep working on the task until it is done.
Is this possible? I tried resource leveling which I thought might help
but it didnt seem to have any luck. The speciality employee also
charges more per hour if that can help microsoft project to figure out
resource allocation.
I posted a similar inquiry a while back and got a response from one
person who thought this was not possible. I think he might be right
but I don't understand why project can't handle that allocation. I
can manually edit the working hours the week of that task (once I know
when the task is starting) but I cant seem to do much else.
Until I get to the task in my schedule it shows that it will take way
longer then it really does. Any ideas on how I can fix