I am very new to MSP 2007 and still learning it day by day.
A have a very first question about the calendars when I plan some pilot
projects.
I have created a new calendar called "Non-Friday" where we work only from
Sunday to Thursday (Friday and Saturday are non-working). I have set the
project calendar to "Non-Friday". The timescale non-working calendar also has
been set to "Non-Friday". The task calendar is also "Non-Friday".
However, when I increase a task duration (scheduled for one day on Thursday)
to 2 days, the Gantt chart shows this task also works on Friday (from
Thursday to Friday). The task type I set is Fixed Units.
Where is the step I am missing? How to schedule the task so that it will not
work on non-working days?
Thanks for any help.
I will probably have more questions when I go along the learning process and
I appreciate all your answers.
Best regards,
Sondin
I am very new to MSP 2007 and still learning it day by day.
A have a very first question about the calendars when I plan some pilot
projects.
I have created a new calendar called "Non-Friday" where we work only from
Sunday to Thursday (Friday and Saturday are non-working). I have set the
project calendar to "Non-Friday". The timescale non-working calendar also has
been set to "Non-Friday". The task calendar is also "Non-Friday".
However, when I increase a task duration (scheduled for one day on Thursday)
to 2 days, the Gantt chart shows this task also works on Friday (from
Thursday to Friday). The task type I set is Fixed Units.
Where is the step I am missing? How to schedule the task so that it will not
work on non-working days?
Thanks for any help.
I will probably have more questions when I go along the learning process and
I appreciate all your answers.