I have a task that was initially assigned to one resource who entered some
time to the task. But a change in the resource has been made and I need to
replace him with a different resource. I went into the plan, selected the
tasks, clicked the Assign Resources icon, selected the resource to change and
clicked Replace. Upon doing so, I got a warning message stating that the
selected task is 100% complete and asking if I want to assign the previously
entered work to the new resource. However, in looking at the % complete
field, it only shows 34% complete.
I inherited the plan from one of our PM's who is no longer here, but I'm
assuming that the task was 100% complete at one time and then more work was
assigned and so project thinks that it is still complete. Does anyone know
if this is true and if so, how to change this?
Thanks!
I have a task that was initially assigned to one resource who entered some
time to the task. But a change in the resource has been made and I need to
replace him with a different resource. I went into the plan, selected the
tasks, clicked the Assign Resources icon, selected the resource to change and
clicked Replace. Upon doing so, I got a warning message stating that the
selected task is 100% complete and asking if I want to assign the previously
entered work to the new resource. However, in looking at the % complete
field, it only shows 34% complete.
I inherited the plan from one of our PM's who is no longer here, but I'm
assuming that the task was 100% complete at one time and then more work was
assigned and so project thinks that it is still complete. Does anyone know
if this is true and if so, how to change this?