OK, so I am new at project.
without linking tasks, how does project schedule out tasks?
If I create 2 resources. And then 3 tasks. each task is 10 days.
I assign 1 task to person 1
I asskign task 2 and 3 to person 2
Now on my gantt chart,
all 3 tasks are assigned for the first 2 weeks.
Without linking tasks, why does it not adjust task 3 to start when person 2
has time?
After task 2 is done?
thanks