task scheduling tracking

H

Hemant

I have Porject 2K and qould like to accomplish the following:

- one column showing the planned duration
- one column showing how many days have been spent on a particular task,
this will be entered daily
- one column showing how many days left to complete a task i.e. uration -
(days spent on a task)

What I envisage is the folloing scenario:

Task Name Planned duration Actual days spent # of days
left
task A 10 7
3
task B 5 25
-20(over ran by 20 days)

Is there a way of getting the MS Project to show these details?

Many thanks in advance.

Hemant
 
J

JulieS

Hi Hemant,

The data you are looking for is already in project.

The "planned Duration" is Baseline Duration - created when you save a
baseline for the task.
How many days have been spent on the task is Actual Duration - supplied when
you track tasks.
How many days left to complete the task is Remaining Duration - calculated
by Project as Baseline Duration - Actual Duration.

The Actual and Remaining Duration fields are already in the Tracking table.
You could easily add the Baseline Duration field or create a custom table to
show just those fields of interest to you.

Hope this helps. Let us know how you get along.

Julie
 