H
Hemant
I have Porject 2K and qould like to accomplish the following:
- one column showing the planned duration
- one column showing how many days have been spent on a particular task,
this will be entered daily
- one column showing how many days left to complete a task i.e. uration -
(days spent on a task)
What I envisage is the folloing scenario:
Task Name Planned duration Actual days spent # of days
left
task A 10 7
3
task B 5 25
-20(over ran by 20 days)
Is there a way of getting the MS Project to show these details?
Many thanks in advance.
Hemant
- one column showing the planned duration
- one column showing how many days have been spent on a particular task,
this will be entered daily
- one column showing how many days left to complete a task i.e. uration -
(days spent on a task)
What I envisage is the folloing scenario:
Task Name Planned duration Actual days spent # of days
left
task A 10 7
3
task B 5 25
-20(over ran by 20 days)
Is there a way of getting the MS Project to show these details?
Many thanks in advance.
Hemant