I am trying to use task sheets in Server PWA for project resources to enter
time spent on takss. Problem is, only individual tasks from the schedule
show up, not summary tasks. This is confusing for the users as they often
cannot distinguish one task from another.
For example if I have this in a schdeule:
Website Policy
Develop
Review
Approve
Coroprate Policy
Develop
Review
Approve
....the tasks show up in the task sheet as:
Develop
Develop
Review
Review
Approve
Approve
Can the task sheet view in PWA be configured to show summary tasks, and if
so how?
Thanks in advance for any help anyone can offer!
time spent on takss. Problem is, only individual tasks from the schedule
show up, not summary tasks. This is confusing for the users as they often
cannot distinguish one task from another.
For example if I have this in a schdeule:
Website Policy
Develop
Review
Approve
Coroprate Policy
Develop
Review
Approve
....the tasks show up in the task sheet as:
Develop
Develop
Review
Review
Approve
Approve
Can the task sheet view in PWA be configured to show summary tasks, and if
so how?
Thanks in advance for any help anyone can offer!