N
Nitesh Mathur
Hiiii every body
I'm using project professional 2003 .My team members (not all, some of them)
facing a problem :---
When they Create a New task against NON development schedule its shows
duplicate in Schedule but in there time sheet its shows as a single task and
portfolio analyzer shows total efforts including duplicate tasks efforts also.
For Example :- When Team member A create a new task named Task A its shows
in his time sheet as Task A of 4hrs but its shows in schedule duplicate. If
member booked 4 hrs as efforts its automatically entered efforts in duplicate
task also.
But one more interesting thing that is other member who are envolve in same
schedule and create a new task they are not facing such type of problem.Only
2-3 out of 14 members facing the problem.
I cant understand what are the possible cause / mistake they r doing.
Kindly provide me the solution ASAP.
I'm using project professional 2003 .My team members (not all, some of them)
facing a problem :---
When they Create a New task against NON development schedule its shows
duplicate in Schedule but in there time sheet its shows as a single task and
portfolio analyzer shows total efforts including duplicate tasks efforts also.
For Example :- When Team member A create a new task named Task A its shows
in his time sheet as Task A of 4hrs but its shows in schedule duplicate. If
member booked 4 hrs as efforts its automatically entered efforts in duplicate
task also.
But one more interesting thing that is other member who are envolve in same
schedule and create a new task they are not facing such type of problem.Only
2-3 out of 14 members facing the problem.
I cant understand what are the possible cause / mistake they r doing.
Kindly provide me the solution ASAP.