N
Naomi Nissen
This is a similar question to another I posed, with a refinement (see
http://groups.google.com/group/microsoft.public.project.server/browse_thread/thread/f9289196cf24b28b)
I want my stoplights in the PWA view to indicate when any TASK within
the project happens to be past its deadline regardless of whether the
entire project is on schedule or not. The stoplight would apply to
the PWA view, so the task does not have to be specified. At the same
token, I want that stoplight to go back to green for the project when
the overdue task is COMPLETED so I know I don't have any tasks within
the project overdue.
Can this be done?
Thanks
Naomi
http://groups.google.com/group/microsoft.public.project.server/browse_thread/thread/f9289196cf24b28b)
I want my stoplights in the PWA view to indicate when any TASK within
the project happens to be past its deadline regardless of whether the
entire project is on schedule or not. The stoplight would apply to
the PWA view, so the task does not have to be specified. At the same
token, I want that stoplight to go back to green for the project when
the overdue task is COMPLETED so I know I don't have any tasks within
the project overdue.
Can this be done?
Thanks
Naomi