T
TooNewToProjectToKnow
I am using Project Standard 2003. I have a 500 task schedule.
The proposal submitted was placed in a project file in a given order.
However, now we need to "resort" the schedule.
I inserted Text1 and input the groupings that I want.. GoupA, GroupB, etc.
Some of these tasks are together, but others are not. GroupA may be tasks
10,11,12,13 and then 121,122, and 200 to 225. Similar for the other groups.
Each of these groups has its own summary task.
I want to regroup the schedule and still keep the same indenture of summary
tasks where practical. This way, all my GroupA is together.
What is the best approach to do this?
The proposal submitted was placed in a project file in a given order.
However, now we need to "resort" the schedule.
I inserted Text1 and input the groupings that I want.. GoupA, GroupB, etc.
Some of these tasks are together, but others are not. GroupA may be tasks
10,11,12,13 and then 121,122, and 200 to 225. Similar for the other groups.
Each of these groups has its own summary task.
I want to regroup the schedule and still keep the same indenture of summary
tasks where practical. This way, all my GroupA is together.
What is the best approach to do this?