K
kahuna
Can anyone provide a solution for this issue, please? I have a
schedule where the PM appears to have run automatic levelling or some
other tweaking that created a split in a task that has nothing
happening for a few months inbetween. I tried to take out the split,
but it always goes back to the split after showing the message that
"Actual hours cannot be updated as we are allowed to update hours only
from the PWA", which is true. I tried delinking, depromoting and
everything inbetween except adjust the actuals to get this to be
normal and it is just not working. Any help is much appreciated.
schedule where the PM appears to have run automatic levelling or some
other tweaking that created a split in a task that has nothing
happening for a few months inbetween. I tried to take out the split,
but it always goes back to the split after showing the message that
"Actual hours cannot be updated as we are allowed to update hours only
from the PWA", which is true. I tried delinking, depromoting and
everything inbetween except adjust the actuals to get this to be
normal and it is just not working. Any help is much appreciated.