M
melmer
Please help, gurus!
Here's the deal: I have fixed duration tasks that may be extended /
shortened on a weekly basis due to progress (though I've disabled and
do not want my tasks to be effort-driven). I have checked "Scheduling
ignores resource calendars" on each of the tasks.
Now when I go to update actual work, I get this message if the actual
work exceeds the baseline work: "The resource is assigned outside of
the original dates for task 14 - the duration will change to
accomodate the resource assignment". The result is my task is
extended another couple of weeks and, if I go to push it back, my
actual work is reduced. YET, my resource assignment units remain the
same, which is what I'd prefer to be adjustable!
What the heck? Is there a way, when I update the actual work, to make
the resource assignment units adjust up to accomodate the actual work
hours instead of the duration increasing?
Thank you -
Martie
Here's the deal: I have fixed duration tasks that may be extended /
shortened on a weekly basis due to progress (though I've disabled and
do not want my tasks to be effort-driven). I have checked "Scheduling
ignores resource calendars" on each of the tasks.
Now when I go to update actual work, I get this message if the actual
work exceeds the baseline work: "The resource is assigned outside of
the original dates for task 14 - the duration will change to
accomodate the resource assignment". The result is my task is
extended another couple of weeks and, if I go to push it back, my
actual work is reduced. YET, my resource assignment units remain the
same, which is what I'd prefer to be adjustable!
What the heck? Is there a way, when I update the actual work, to make
the resource assignment units adjust up to accomodate the actual work
hours instead of the duration increasing?
Thank you -
Martie