dee
Hi All
I want to share and ask about task splitting. Resource is assigned for :
task B at August 6
But he enters the actual work at timesheet in August 3, Then he submits the
the timesheet, was approved by Timesheet Manager. He imports timeheet to task
and submit the task. The PM approves task update. The PM open the MS Project
Professional , the result, automatically, the task splitting because the
uncorrect filled
The resource recall the timesheet to repair the mistake, and update the
actual work in August 6, and delete the actual work at August 3, then he
submits the timesheet. The timesheet Manager approved timesheet. The resource
import timesheet to task and then submit task. PM approve task update. Th PM
open the Project Profesional but it's same like before. The task is still
split.
What can I do to repair the mistake?
Thanks a lot for your help
Regard
Dy
I want to share and ask about task splitting. Resource is assigned for :
task B at August 6
But he enters the actual work at timesheet in August 3, Then he submits the
the timesheet, was approved by Timesheet Manager. He imports timeheet to task
and submit the task. The PM approves task update. The PM open the MS Project
Professional , the result, automatically, the task splitting because the
uncorrect filled
The resource recall the timesheet to repair the mistake, and update the
actual work in August 6, and delete the actual work at August 3, then he
submits the timesheet. The timesheet Manager approved timesheet. The resource
import timesheet to task and then submit task. PM approve task update. Th PM
open the Project Profesional but it's same like before. The task is still
split.
What can I do to repair the mistake?
Thanks a lot for your help
Regard
Dy