Task Start Date Deadline

S

Saviz

Hi,
Is there a way to set a Start date deadline? (I know you can set a finish
date deadline).

I want to avoid using constraints yet have a warning indicator showing that
task start date delayed...

Thanks,
 
M

Mike Glen

Hi Saviz,

Welcome to this Microsoft Project newsgroup :)

Why not set a milestone prior to the task and set a deadline on that?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
S

Steve House

But another way of looking at it, does it really matter when a task starts
as long as it finishes on time?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top