K
Konstantin
Hi,
I've got a little problem.
In WBS I have 11 similar tasks (programming). All of them goes one
after another.
Task number 10 has start date (calculated) at 05.08.09 (DD.MM.YY) and
finish date 08.08.09.
But responsible user completed that task much earlier (at 17.07.09). I
approved his timesheet and after publication task number 10 marked as
100% completed.
But the problem is that task 11 still has same start date as before
(09.09.09). What did I wrong and is there any way to make tasks start
moving towards the date of predecessor's end?
Thank you
I've got a little problem.
In WBS I have 11 similar tasks (programming). All of them goes one
after another.
Task number 10 has start date (calculated) at 05.08.09 (DD.MM.YY) and
finish date 08.08.09.
But responsible user completed that task much earlier (at 17.07.09). I
approved his timesheet and after publication task number 10 marked as
100% completed.
But the problem is that task 11 still has same start date as before
(09.09.09). What did I wrong and is there any way to make tasks start
moving towards the date of predecessor's end?
Thank you