I recently was rolled from NT to XP and upgraded from
Project 98 to Project Professional 2002. When I
originally created the projects in 98, they displayed
Day, Date, Time in both the Start & Finish fields. Now
when I open them they display only the day and the date.
I have chosen the "Format" "Layout" menu and it shows
that what I need is the way that it is set , but still
the Gantt actually displays only the day and the date. I
have expanded the field with hope that they were hiding,
but they were not.
Any ideas as to how I might recover the actual start and
finish times?
 
M

Mike Glen

Hi Chaps,

Welcome to this Microsoft Project newsgroup :)

Tools/Options.../View tab/Date format: select a date format that includes
the time.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
C

Chaps

Mike,

That was the ticket! Thanks for the help, I guess
sometimes we just get a mental block when trying to do
something that we have done so many times before.
 