Our organization is in the process of implementing Project Server 2007, and I
have been given the job of "figuring out how to use it". One oddity I have
noticed is that even though permissions, risks, and issues are synchronized
from PWA to the Project Workspaces, the task assignments are not. Either I
have misunderstood the purpose of "Tasks" in the workspaces, or something is
misconfigured.

I have left the check-box "checked" under "Project Workspace Provisioning
Settings" that allows it to sync with pwa. Any ideas?
 
G

Gary L. Chefetz

BudOlly:

You have, indeed, misunderstood the purpose of tasks in the Project
Workspace. This is available for the team to track tasks that are not
associated with the project plan. IME, very few customers use this task list
in the Project Workspaces.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top