J
jay
desktop: MS Project Professional 2002 SP-1
server: MS Project Server 2003 SP-1
Background: Project Owner had set a Task to 100% Work Complete, saved
project and published to web. In PWA, Resource's timesheet still showed Task
as 0% Work Complete and 947 Remaining Hours. Only one Resource had been
assigned to the Task.
Troubleshoot task synchronization issue: In order to confirm that the
project had been published to the web, we republished. First, with method
"New and Changed Assignments" (no changes were shown to be published) and
then with method "Project Plan". Task still shows 0% Work Complete and 947
Remaining Hours.
Advice is welcomed. Thank you in advance.
server: MS Project Server 2003 SP-1
Background: Project Owner had set a Task to 100% Work Complete, saved
project and published to web. In PWA, Resource's timesheet still showed Task
as 0% Work Complete and 947 Remaining Hours. Only one Resource had been
assigned to the Task.
Troubleshoot task synchronization issue: In order to confirm that the
project had been published to the web, we republished. First, with method
"New and Changed Assignments" (no changes were shown to be published) and
then with method "Project Plan". Task still shows 0% Work Complete and 947
Remaining Hours.
Advice is welcomed. Thank you in advance.