C
Chris
My organisation runs both My Tasks and My Timesheets. My Timesheets is used
to capture the work performed and billable hours to a job, My Tasks is set
to percentage complete.
Our processes want all resources to update their My Tasks daily, including
hours remaining. All resources only need to update their Timesheets weekly.
I have reviewed all PWA setting and have attempted to 'unlink' My Tasks and
My Timesheet, but when a resource "Adds Line" in My Timesheet and picks a
particular task, the line is auto-populated with the task progress
(inlcuding hours worked).
So how do I get PWA to allow task entry in My Timesheets without
Autopopulation from My Tasks.
to capture the work performed and billable hours to a job, My Tasks is set
to percentage complete.
Our processes want all resources to update their My Tasks daily, including
hours remaining. All resources only need to update their Timesheets weekly.
I have reviewed all PWA setting and have attempted to 'unlink' My Tasks and
My Timesheet, but when a resource "Adds Line" in My Timesheet and picks a
particular task, the line is auto-populated with the task progress
(inlcuding hours worked).
So how do I get PWA to allow task entry in My Timesheets without
Autopopulation from My Tasks.