Task Total Duration in Ms project(Including holidays)

Joined
Aug 29, 2013
Messages
1
Reaction score
0
Cool evening to all,
I am a new bird for the Ms project. I have a doubt and hope you will give a solution. May be this is a simple one, i have made a schedule by changing standard calendar based on my project working and non working days..Now i want total duration for my project(includes holidays/non working days). Is it possible? if so , could you pls share with me..

Thanks in advance.

Murugan
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top