B
Bud
We are using MSPS Project 2007
We have production support schedules with some non-direct tasks such as Team
Meetings, ADMIN, General client support, etc that we set up for the year
through 12/31/2008 with Task Types of Fixed Duration.
We also have small change request tasks that we have set up as Fixed units.
Actuals are posted to the schedule through timesheets and this happens
automatically.
We progress our schedules each week since many of the tasks are of course
just forecasts of what we think will happen. Some work just doesn't happen
and we need to move it forward since you can't physically do work yesterday.
We do this by going to Tools, Tracking, Reschedule uncompleted work to start
after...option. We progress the whole schedule because we want to see what
actually is happening on all types of tasks and than perhaps make some
adjustments.
This moves work on the Fixed duration types of tasks out to let's say
1/9/2009. We than simply change the Finish date back to 12/31/2008.
When we do this it changes the Task type from Fixed duration to Fixed Units
and than we have to change it back.
Why is it doing this? What can we do to prevent it?
Thanks
We have production support schedules with some non-direct tasks such as Team
Meetings, ADMIN, General client support, etc that we set up for the year
through 12/31/2008 with Task Types of Fixed Duration.
We also have small change request tasks that we have set up as Fixed units.
Actuals are posted to the schedule through timesheets and this happens
automatically.
We progress our schedules each week since many of the tasks are of course
just forecasts of what we think will happen. Some work just doesn't happen
and we need to move it forward since you can't physically do work yesterday.
We do this by going to Tools, Tracking, Reschedule uncompleted work to start
after...option. We progress the whole schedule because we want to see what
actually is happening on all types of tasks and than perhaps make some
adjustments.
This moves work on the Fixed duration types of tasks out to let's say
1/9/2009. We than simply change the Finish date back to 12/31/2008.
When we do this it changes the Task type from Fixed duration to Fixed Units
and than we have to change it back.
Why is it doing this? What can we do to prevent it?
Thanks