I have a milestone task in my plan with the start and finish date on Oct 25.
I then create another task with work estimated of 6 hours and put in the
predecessor the milestone task (SS). Shouldn't the start date of the new
task be on the 25th too? Why does it shift to 10/26?
I'd appreciate a responese ASAP
1 milestone task 0 hrs 10/25 10/25
2 test task 6hrs 10/26 10/26 1SS
Thanks!