task type start-start (SS) - Urgent request

A

anams

I have a milestone task in my plan with the start and finish date on Oct 25.
I then create another task with work estimated of 6 hours and put in the
predecessor the milestone task (SS). Shouldn't the start date of the new
task be on the 25th too? Why does it shift to 10/26?

I'd appreciate a responese ASAP

1 milestone task 0 hrs 10/25 10/25
2 test task 6hrs 10/26 10/26 1SS

Thanks!
 
B

Ben Howard

The milestone probably finishes at 17:00. Edit the table so that the start
and finish date format includes the time, and then change the start time to
09:00 or whatever matches the calendar.

That'll sort it.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top