I
ITByte
Ok,,,, I'm green, and just can't get something to click. We need to be able
to assign resources to tasks among many projects, and allow the user to work
on the task within a given time frame. Example: There is a month to do the
task Start-Finish, but I only need 14hrs of time from the resource. The
resource can work on the task 1hr a day for 14 days, 7hrs for 2 days, and it
doesn't matter as long as the due date is meet. I'v play with slack time to
accomplish the padding, but I can't seem to get it to work. It seems that
Project assumes the task will be worked on start to finish based on the
duration.
Thanks
Greg
to assign resources to tasks among many projects, and allow the user to work
on the task within a given time frame. Example: There is a month to do the
task Start-Finish, but I only need 14hrs of time from the resource. The
resource can work on the task 1hr a day for 14 days, 7hrs for 2 days, and it
doesn't matter as long as the due date is meet. I'v play with slack time to
accomplish the padding, but I can't seem to get it to work. It seems that
Project assumes the task will be worked on start to finish based on the
duration.
Thanks
Greg