Hi all.
I'm basically a Project newbie... I'm searched through archived posts for
this group and couldn't find an answer to this question.
BACKGROUND: I work in an admissions office at a college. We're using
Project to manage the office deliverables from getting applications in to
getting decisions out.
ISSUE: On an application deadline, the processing team (that I oversee)
begins to do all kinds of magic to each individual file. The processing
time for the whole batch depends on the total number of applications we
receive (more apps, more processing time). In addition, another team in the
office responsible for reviewing applications can only begin work once we
have processed a 'critical mass' of files for them.
HOPE: We can set up our calendar based on estimated inbound applications to
start with. Once the actual application number is known, we would love ot
be able to change the 'input' number in Project and have the calendar update
automagically to reflect the real timeline.
QUESTIONS:
1) Is it possible to tell Project that a task's length should be calculated
based on (in this case) # of applications divided by expected daily output?
I would figure that this is a 'fixed work' task where units would equal the
number of applications, but I can't seem to nail down how to set it up.
2) Can you set a dependant task to begin once 100 'units' of the other task
have been completed? In my case, this would be setting the reading/review
of the applications to begin once ~100 applications have been completely
processed by my team.
I look forward to reading your posted responses... And I thank you *very
very* much for your help!
Sincerely, Mouse
I'm basically a Project newbie... I'm searched through archived posts for
this group and couldn't find an answer to this question.
BACKGROUND: I work in an admissions office at a college. We're using
Project to manage the office deliverables from getting applications in to
getting decisions out.
ISSUE: On an application deadline, the processing team (that I oversee)
begins to do all kinds of magic to each individual file. The processing
time for the whole batch depends on the total number of applications we
receive (more apps, more processing time). In addition, another team in the
office responsible for reviewing applications can only begin work once we
have processed a 'critical mass' of files for them.
HOPE: We can set up our calendar based on estimated inbound applications to
start with. Once the actual application number is known, we would love ot
be able to change the 'input' number in Project and have the calendar update
automagically to reflect the real timeline.
QUESTIONS:
1) Is it possible to tell Project that a task's length should be calculated
based on (in this case) # of applications divided by expected daily output?
I would figure that this is a 'fixed work' task where units would equal the
number of applications, but I can't seem to nail down how to set it up.
2) Can you set a dependant task to begin once 100 'units' of the other task
have been completed? In my case, this would be setting the reading/review
of the applications to begin once ~100 applications have been completely
processed by my team.
I look forward to reading your posted responses... And I thank you *very
very* much for your help!
Sincerely, Mouse