Task Update changes finish date when using fixed duration

C

Christina

Hi,

when a team member sents a task update and it is approved the finish date
changes according to tasks duration. The plan has baseline values. The thing
is that in PWA My Tasks the team member sees the new extended finish date
instead of the baseline finish. This is misleading for tne team member. Is
there a possibility of showing in My Tasks the baseline dates? Or any
workaround solution. The only solution we came up with is for project
managers to change the finish date in the plan which when dealing with many
projects and day to day work is very time consuming.
 
D

Dale Howard [MVP]

Christina --

The Project Server administrator can edit the My Assignments view and add
the Baseline Finish field to the View. Hope this helps.
 
D

Dale Howard [MVP]

Christina --

Nope. That's not what I mean. The View that users see on the My Tasks page
is actually called the My Assignments view. The Project Server
administrator must edit that View. Hope this helps.
 