A
Angel
In the process of migrating from 2003 to 2007, we witnessed Task Updates
submitted for projects created in the 2007 enviornment would only display
Actual Hours not yet approved by the PM starting from the earliest date
submitted to the latest date.
Unfortunately, Task Updates on migrated projects display the earliest date
ever worked on each project. So the PM must always change the date range in
order to see what a resource has recently charged displayed in red.
Is there anything that can be done to automate the date range displayed so
that the PM approving Actual Work only sees new updates instead of all hours
charged to a project? Or is there a Task Display setting that we've changed
that must be reverted back to default?
submitted for projects created in the 2007 enviornment would only display
Actual Hours not yet approved by the PM starting from the earliest date
submitted to the latest date.
Unfortunately, Task Updates on migrated projects display the earliest date
ever worked on each project. So the PM must always change the date range in
order to see what a resource has recently charged displayed in red.
Is there anything that can be done to automate the date range displayed so
that the PM approving Actual Work only sees new updates instead of all hours
charged to a project? Or is there a Task Display setting that we've changed
that must be reverted back to default?