Task Update Discrepency in PS07

J

JP

We've noticed a few discrepencies on task task updates in PS07.
Here's what's happening:
A resource submitts a task update with actual hours entered for a specific
date, say 3/15. When the PM goes to approve this update, he sees the hours
on 3/16 rather than 3/15.
We double checked with the resource and viewed his My Tasks page to see if
he entered his hours on 3/15... and he did.
So why would the project manager receive the update with hours on 3/16?

The next day, the resources hours had moved from 3/15 to 3/16 on his My
Tasks page. We've seen this happen a few times now with different resources.
Any thought as to why this happens?
 