Task Update History

S

Stacey

Hi!

We use MS Project 2007 and we are having an issue getting resources to
report their hours every day. Is there a history report that would show us
the history of which days each resource reported their time?

Thank you!
Stacey
 
J

Jonathan Sofer [MVP]

Sorry but Project Server 2007 does not have those kind of detailed logging
capabilities.

Are you using My Timesheets or My Tasks or both? If you are using My
Timesheets, you might be able to create an SSRS or Data Analysis report that
shows which days the resources have reported hours against.

Jonathan
 
S

Stacey

Thanks Jonathan!

We use My Tasks. I can always do the report manually, it just takes time.

Thanks for your response!
Stacey
 