Task Update Progress Calendar

H

Haley M

Hello,

I went into Project Server today and I noticed the calendar, in the my tasks
view, starts on Tuesday?? I haven't changed anything in the settings and
checked my task settings and display and the reporting display has "week
starts on: Monday".

Any thoughts on what is prompting this change?

Thank you!
Haley
 
D

Dale Howard [MVP]

Haley --

This sounds like your company is using Project Server 2007 with Service Pack
1 installed, but without the Infrastructure Update or any later cumulative
updates applied. After SP1 and prior to the Infrastructure Update, the
timesheet grid in the My Tasks page "shifted" to the left to keep the
current date centered in the grid. This is why you don't see Monday,
because Friday is now the middle day in the grid. It sounds like it is time
for your company to get all the latest updates applied to your Project
Server 2007 system. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top