K
Kurt Petteloot
Hi,
For some specific type of tasks our PM's like to work with fixed duration
tasks, in order to keep the finish date fixed regardless of actuals recorded
on the task. In practice however the task finish date is pushed ino the
future when actuals are entered. The tasks are 'fixed duration'.
Is there a way to avoid that actuals being accepted results in a shift of
the finish date, so that the PM is obliged to reset the duration of these
tasks back to it's oroginal value.
thanks.
Kurt Petteloot
For some specific type of tasks our PM's like to work with fixed duration
tasks, in order to keep the finish date fixed regardless of actuals recorded
on the task. In practice however the task finish date is pushed ino the
future when actuals are entered. The tasks are 'fixed duration'.
Is there a way to avoid that actuals being accepted results in a shift of
the finish date, so that the PM is obliged to reset the duration of these
tasks back to it's oroginal value.
thanks.
Kurt Petteloot