Task update screen

P

Poni

Hello,

At PWA 2007, I want to get an updates from resources.
The screen stuck in loading grid so I can't see anything.

Please advice.

P.
 
J

Jennifer Penn

Hello,

At PWA 2007, I want to get an updates from resources.
The screen stuck in loadinggridso I can't see anything.

Please advice.

P.

Hi Poni, have you had any luck with this? I am having the same issue
with my test server, but my user account is the only one experiencing
the issue.
 
J

Jennifer Penn

Hi Poni, have you had any luck with this?  I am having the same issue
with my test server, but my user account is the only one experiencing
the issue.

I just solved my problem! It appears that a resource reported time to
a summary task. The summary task was created by the resource and time
was reported to the task. once i deleted the task from the project
plan, the accept time page began to load properly.
 