J
jackie
Hello
I have a task that lasts 5 days, from Monday to Friday, 1 resource allocated
to it, for 8 hours a day, with a total of hours of 40.
On Wednesday, I update the percentage field by 20% as the resource has only
been able to work 8 hours on this task. In my logic 40 hours minus 20% leaves
with 32 hours. These 32 hours would then plotted across the remaining
duration of the task.
How does MS Project resolve this situation?
Any help would be much appreciated
Many thanks
Ilaria
I have a task that lasts 5 days, from Monday to Friday, 1 resource allocated
to it, for 8 hours a day, with a total of hours of 40.
On Wednesday, I update the percentage field by 20% as the resource has only
been able to work 8 hours on this task. In my logic 40 hours minus 20% leaves
with 32 hours. These 32 hours would then plotted across the remaining
duration of the task.
How does MS Project resolve this situation?
Any help would be much appreciated
Many thanks
Ilaria