K
Kerry
We're just planning how to update tasks. We have decided not to do the 2 step
timesheets and tasks update, becuase it's more than we want, or need to take
on.
We have about 700 resources, of which half are doing maintenance type
activities. We've already got about 300 resources who work on project work,
assigned to tasks, and we're piloting 1 team entering actuals hours thru Web
Access, with the Project manager approving them.
For maintenance we plan to setup ongoing type tasks for those resources to
update. That way we can still capture overall orgnazational metrics. Here's
my question is there any way to have someone assigned as a status manager,
that doesn't have Project Pro? Currently we have about 40 maintenance
resource managers who would only be using Pro to setup high level plans, to
approve time for their resoucrces. They could use Web Access Approval. I
know you can't change the status manager to anone but the person opening the
plan. Is there another method?
timesheets and tasks update, becuase it's more than we want, or need to take
on.
We have about 700 resources, of which half are doing maintenance type
activities. We've already got about 300 resources who work on project work,
assigned to tasks, and we're piloting 1 team entering actuals hours thru Web
Access, with the Project manager approving them.
For maintenance we plan to setup ongoing type tasks for those resources to
update. That way we can still capture overall orgnazational metrics. Here's
my question is there any way to have someone assigned as a status manager,
that doesn't have Project Pro? Currently we have about 40 maintenance
resource managers who would only be using Pro to setup high level plans, to
approve time for their resoucrces. They could use Web Access Approval. I
know you can't change the status manager to anone but the person opening the
plan. Is there another method?