Task Updates - Date Range

M

m2mteck

I'm using PS2007...

In PWA | Approvals | Task Updates, is there a way to change the defaulted
dates in the Date Range fields. Mine are defaulting 11/11/2008 to 3/31/2010.
I have to change them everytime and was wondering if there's some place I or
the system admin can change the default to at least 1/1/2010 to 3/31/2010? In
my situation, it doesn't matter if it's an indivisional setting or a setting
that everyone will benefit from.

Along the same lines...
I am using the timesheet cube and the Time field lists 1994 all the way to
2049. Is there a way to change this to 2008 to 2049? You have to scroll down
to 2009 or 2010 then drill down to quarters, etc.
 
B

Ben

No sure about 1, but for 2, pre-set the dates in the view (server settings)
for the current year/period. That way you'll only need to change it once per
period, rather than each time....
 
D

Dale Howard [MVP]

m2mteck --

The starting date on the Task Updates page defaults to the Start date of the
earliest starting in-progress task. Do you have a task that is still
currently in-progress that started on 11/11/2008 and is scheduled to finish
on 3/31/10, by chance? If so, there is no way to change how the system
works. Hope this helps.
 