M
m2mteck
I'm using PS2007...
In PWA | Approvals | Task Updates, is there a way to change the defaulted
dates in the Date Range fields. Mine are defaulting 11/11/2008 to 3/31/2010.
I have to change them everytime and was wondering if there's some place I or
the system admin can change the default to at least 1/1/2010 to 3/31/2010? In
my situation, it doesn't matter if it's an indivisional setting or a setting
that everyone will benefit from.
Along the same lines...
I am using the timesheet cube and the Time field lists 1994 all the way to
2049. Is there a way to change this to 2008 to 2049? You have to scroll down
to 2009 or 2010 then drill down to quarters, etc.
In PWA | Approvals | Task Updates, is there a way to change the defaulted
dates in the Date Range fields. Mine are defaulting 11/11/2008 to 3/31/2010.
I have to change them everytime and was wondering if there's some place I or
the system admin can change the default to at least 1/1/2010 to 3/31/2010? In
my situation, it doesn't matter if it's an indivisional setting or a setting
that everyone will benefit from.
Along the same lines...
I am using the timesheet cube and the Time field lists 1994 all the way to
2049. Is there a way to change this to 2008 to 2049? You have to scroll down
to 2009 or 2010 then drill down to quarters, etc.