S
Sam
Hello everybody,
I have two very serious problems getting the actual work from task updates
into the Project Client.
We use Project Server 2007 with the following procedure: Working time is
entered in the timesheet and imported to My Tasks using the Import Timesheet
function. Users send their task updates here after editing the remaining time
and selecting the tasks. Now I can see the updates in PWA Task Updates. I
open the project in Project Client, accept all Task Updates and choose to
apply the changes to the project plan.
Sometime everything works fine, but somtimes one of the two problems appears:
Problem 1:
The "Applying Update" dialog appears and counts down from 30 secondes. After
reaching 0 secondes it restarts counting down from 30. This seems to be an
infinite loop - after several hours waiting nothing has changed.
The PWA Manage Queue Jobs shows one entry. This entry refers to this task
update and contains the following values:
Queue Entry Time:9/25/2007 11:29 AM; Queue Completed Time: 9/25/2007 11:29
AM; Job Type:Job Type:Status Update; Job State:Skipped For Optimization; %
complete:20%; Queue Position:N/A, Queue Typeroject; Error:empty
I tried Retry Job as well as Cancel Job in Manage Queue Jobs in PWA, but it
does not change anything. I can not delete the job from the queue. Other jobs
are performed.
Surprisingly this time the actual work was shown in the project plan after I
have closeed and reopened the project client and opened the project.
Problem 2:
The "Applying Update" dialog appers. After it is finished I coose to open
the Project Plan in Project Client to see the applied changes. But the
project plan shows NO actual Work from any of task updates that have just
been approved.
The submited task updates are no longer shown in PWA Task Updates. The queue
showes no entry.
I assume that the not working preview function during the task approval does
indicate that problem 2 will occure. But I am not sure, because I cannot
reproduce this behavior either with this nor an other project.
Any help would be appreciated! Thanks a lot!
I have two very serious problems getting the actual work from task updates
into the Project Client.
We use Project Server 2007 with the following procedure: Working time is
entered in the timesheet and imported to My Tasks using the Import Timesheet
function. Users send their task updates here after editing the remaining time
and selecting the tasks. Now I can see the updates in PWA Task Updates. I
open the project in Project Client, accept all Task Updates and choose to
apply the changes to the project plan.
Sometime everything works fine, but somtimes one of the two problems appears:
Problem 1:
The "Applying Update" dialog appears and counts down from 30 secondes. After
reaching 0 secondes it restarts counting down from 30. This seems to be an
infinite loop - after several hours waiting nothing has changed.
The PWA Manage Queue Jobs shows one entry. This entry refers to this task
update and contains the following values:
Queue Entry Time:9/25/2007 11:29 AM; Queue Completed Time: 9/25/2007 11:29
AM; Job Type:Job Type:Status Update; Job State:Skipped For Optimization; %
complete:20%; Queue Position:N/A, Queue Typeroject; Error:empty
I tried Retry Job as well as Cancel Job in Manage Queue Jobs in PWA, but it
does not change anything. I can not delete the job from the queue. Other jobs
are performed.
Surprisingly this time the actual work was shown in the project plan after I
have closeed and reopened the project client and opened the project.
Problem 2:
The "Applying Update" dialog appers. After it is finished I coose to open
the Project Plan in Project Client to see the applied changes. But the
project plan shows NO actual Work from any of task updates that have just
been approved.
The submited task updates are no longer shown in PWA Task Updates. The queue
showes no entry.
I assume that the not working preview function during the task approval does
indicate that problem 2 will occure. But I am not sure, because I cannot
reproduce this behavior either with this nor an other project.
Any help would be appreciated! Thanks a lot!