D
Deshwal - Magus India
Hi,
I fill in my resource timesheet ..work: 50 hrs ...actual work: 40 hrs
.....save timesheet.
Now i go to task update: import timesheet data .. %complete is calculated to
80% ... i go and change remaining work to 20 hrs ..and recalculate and save
... the %complete still remains 80% ....
I fill in my resource timesheet ..work: 50 hrs ...actual work: 40 hrs
.....save timesheet.
Now i go to task update: import timesheet data .. %complete is calculated to
80% ... i go and change remaining work to 20 hrs ..and recalculate and save
... the %complete still remains 80% ....