R
Radu
Hi all,
I have the following scenario:
One project: Project1
One task: Task1, estimated duration 16h
One resource: Resource1, full rights, member of all groups
Task1 is assigned to Resource1 (only)
Resource1 creates a timesheet with 8h of work for Task1, saves and submit.
The timesheet displays the remaining work column. Resource1 leave this
unchanged.
From My Tasks, Resource 1 imports the newly created timesheet to Task1 and
clicks Submit All.
In Task Updates there is nothing to Approve for Resource1.
In Project Center, the actual work reported is NOT reflected. Though, if
Resource1 opens Project1 in Microsoft Project (windows client) the actual
work done for Task1 is 8h (witch is very correct).
Only after Resource1 publish Project1, the work done for Task1 is reflected
in Project Center.
Is this a bug ?
Can this behaviour be related to this KB Article ?
http://support.microsoft.com/default.aspx/kb/956061
Thank you!
I have the following scenario:
One project: Project1
One task: Task1, estimated duration 16h
One resource: Resource1, full rights, member of all groups
Task1 is assigned to Resource1 (only)
Resource1 creates a timesheet with 8h of work for Task1, saves and submit.
The timesheet displays the remaining work column. Resource1 leave this
unchanged.
From My Tasks, Resource 1 imports the newly created timesheet to Task1 and
clicks Submit All.
In Task Updates there is nothing to Approve for Resource1.
In Project Center, the actual work reported is NOT reflected. Though, if
Resource1 opens Project1 in Microsoft Project (windows client) the actual
work done for Task1 is 8h (witch is very correct).
Only after Resource1 publish Project1, the work done for Task1 is reflected
in Project Center.
Is this a bug ?
Can this behaviour be related to this KB Article ?
http://support.microsoft.com/default.aspx/kb/956061
Thank you!