Task Updates not showing in grid

M

Mike

Question if anyone has seen this. I have a project plan, where after the team
submitted their task updates, we changed the status manager on the plan.
Now, when the status manager open the plan, he gets the warning "Team members
have submitted 63 new updates". The grid shows up - but it is empty - no
task there to approve. If the previous status manager open the plan, same
thing happens - new updates, but cannot approve them. how can we get this
time to get approved on the plan?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top