Hi,
Used to work but since a few days ago we have not been able to update tasks
using My Tasks; the updates do not display in the project plan an longer.
After submitting the task, and trying to update the plan, we go to review the
My Task page and we find that the finish date for the task(s) are changed
automatically to 1/1/2005, and %complete goes back to zero (we are using
%complete and we do not edit dates in My Tasks).
We've tried using project new files, we've tried changing the task type we
are using...
We have another server environment that works fine.
What can it be that has been messed up? How do we fix it? Is a call to
Microsoft in order?
/Spiro
Used to work but since a few days ago we have not been able to update tasks
using My Tasks; the updates do not display in the project plan an longer.
After submitting the task, and trying to update the plan, we go to review the
My Task page and we find that the finish date for the task(s) are changed
automatically to 1/1/2005, and %complete goes back to zero (we are using
%complete and we do not edit dates in My Tasks).
We've tried using project new files, we've tried changing the task type we
are using...
We have another server environment that works fine.
What can it be that has been messed up? How do we fix it? Is a call to
Microsoft in order?
/Spiro