Task updates not working

S

ST

Hi,

Used to work but since a few days ago we have not been able to update tasks
using My Tasks; the updates do not display in the project plan an longer.
After submitting the task, and trying to update the plan, we go to review the
My Task page and we find that the finish date for the task(s) are changed
automatically to 1/1/2005, and %complete goes back to zero (we are using
%complete and we do not edit dates in My Tasks).

We've tried using project new files, we've tried changing the task type we
are using...

We have another server environment that works fine.

What can it be that has been messed up? How do we fix it? Is a call to
Microsoft in order?

/Spiro
 
A

Andre Venter

Spiro ,

Have you persued the event logs as yet , not only the project Queue but the
actual server event logs for any strange events ? What version of Project are
we talking about ?? 2003 ?? 2007 ?? What service Pack are you currently on.
Please give us feedback and we will be able to better assist you.
--
Andre Venter
Technical Consultant
UMT South Africa
MCP
MCSE 2000
MCITP Project
MCTS Managing Projects
MCTS Confiuring Project Server
MCTS Charter Member
MCTS MOSS
MCITP Charter member
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top