Hi all:
From time to time I got the task updates problem in my plans.
In our project team, we use both the timesheets and the task updates. The
engineer will first input their hours in timesheets and then from "my task",
they import the timesheet to task updates and then submit both timesheets and
task updates to the project manager to approve.
Most of the time it works just fine. But from time to time, the import of
timesheet hours doesn't work. After importing, the hours of some tasks are
not really imported. 90% of time it could be solved by deleting the timesheet
and start all over again. But some extreme cases, even deleting timesheet
doesn't works. In this case, the project managers have create the new tasks
for booking.
Does anyone experience the similar issue as we do? Does anyone know if it is
a known issue and if there is any way to solve it?
Thanks
Rock
From time to time I got the task updates problem in my plans.
In our project team, we use both the timesheets and the task updates. The
engineer will first input their hours in timesheets and then from "my task",
they import the timesheet to task updates and then submit both timesheets and
task updates to the project manager to approve.
Most of the time it works just fine. But from time to time, the import of
timesheet hours doesn't work. After importing, the hours of some tasks are
not really imported. 90% of time it could be solved by deleting the timesheet
and start all over again. But some extreme cases, even deleting timesheet
doesn't works. In this case, the project managers have create the new tasks
for booking.
Does anyone experience the similar issue as we do? Does anyone know if it is
a known issue and if there is any way to solve it?
Thanks
Rock