T
Trivikram
Hi...
I want know if there is a way to accept task updated for a certain time
period out of the submitted. For example, lets say a resource submitted
updates for 4 wks at a time and I want accept the last 3 wks & reject the 1st
week time for that resource.
Thanks in advance,
Trivikram.
I want know if there is a way to accept task updated for a certain time
period out of the submitted. For example, lets say a resource submitted
updates for 4 wks at a time and I want accept the last 3 wks & reject the 1st
week time for that resource.
Thanks in advance,
Trivikram.