N
Nehal
Is there any easy way to have resources update tasks
using web access?
They have to use some strange combination of %complete
and remaining hours to accurately depict whats going on.
The % complete works great when things are on schedule.
If not it is complex to follow.
For Eg Task A given to Resource 1 for 4 days.
If this task takes 5 days to complete how does this
resource update web access. (it is easier to update this
in Project Pro 03 - thick client).
Thoughts?
Nehal
using web access?
They have to use some strange combination of %complete
and remaining hours to accurately depict whats going on.
The % complete works great when things are on schedule.
If not it is complex to follow.
For Eg Task A given to Resource 1 for 4 days.
If this task takes 5 days to complete how does this
resource update web access. (it is easier to update this
in Project Pro 03 - thick client).
Thoughts?
Nehal