After installing (and maybe before but never noticed) SP2 and the April CU I
began to notice the tasks updates page locking up if I only accepted a
portion of the submitted updates. If I accept all updates everything works
just fine. However, if I do not accept a couple of the submitted updates and
attempt to apply a portion of the updates the web part fails to complete the
update (the schecule actually gets updated just the page fails to complete
the process).
And today I received an error message saying "To display the webpart again,
IE needs to resend the infor you've previously submitted. If you were making
a purchase....etc."
This has occured each time I have only accepted only a portion of the
submitted updates and to fix it I have to submit updates and accept them all
or the Task Updates page just sits there with "Loading updates..." on the
screen.
Anyone else seeing this?
Darrell
After installing (and maybe before but never noticed) SP2 and the April CU I
began to notice the tasks updates page locking up if I only accepted a
portion of the submitted updates. If I accept all updates everything works
just fine. However, if I do not accept a couple of the submitted updates and
attempt to apply a portion of the updates the web part fails to complete the
update (the schecule actually gets updated just the page fails to complete
the process).
And today I received an error message saying "To display the webpart again,
IE needs to resend the infor you've previously submitted. If you were making
a purchase....etc."
This has occured each time I have only accepted only a portion of the
submitted updates and to fix it I have to submit updates and accept them all
or the Task Updates page just sits there with "Loading updates..." on the
screen.
Anyone else seeing this?