task updates

S

shima

hi;
thanks for your last response.now i have a new problem.when my users submit
their updates and send them to me and i accept them,changes will appear in my
tasks page, but if i want to reject them and changes my last updates,it
doesnt reflect to my tasks and last changes appear.for example task A
completed 4% by my last acceptance and i want to reject this accept and it
becomes 0% but in my task i see 4% completed.how can i refresh my tasks page?
thanks alot
 
D

Dale Howard [MVP]

shima --

After you approve the changes from the Task Updates page in PWA, you need to
open the project in Microsoft Project 2007 and publish the latest schedule
changes using File - Publish. It sounds like you are not doing this
important step. Hope this helps.
 