hi;
thanks for your last response.now i have a new problem.when my users submit
their updates and send them to me and i accept them,changes will appear in my
tasks page, but if i want to reject them and changes my last updates,it
doesnt reflect to my tasks and last changes appear.for example task A
completed 4% by my last acceptance and i want to reject this accept and it
becomes 0% but in my task i see 4% completed.how can i refresh my tasks page?
thanks alot
thanks for your last response.now i have a new problem.when my users submit
their updates and send them to me and i accept them,changes will appear in my
tasks page, but if i want to reject them and changes my last updates,it
doesnt reflect to my tasks and last changes appear.for example task A
completed 4% by my last acceptance and i want to reject this accept and it
becomes 0% but in my task i see 4% completed.how can i refresh my tasks page?
thanks alot