task updates

S

shima

hi;
thanks for your last response.now i have a new problem.when my users submit
their updates and send them to me and i accept them,changes will appear in my
tasks page, but if i want to reject them and changes my last updates,it
doesnt reflect to my tasks and last changes appear.for example task A
completed 4% by my last acceptance and i want to reject this accept and it
becomes 0% but in my task i see 4% completed.how can i refresh my tasks page?
thanks alot

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...90a5-6a37e28c8d06&dg=microsoft.public.project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top