Task Usage and Resource Usage Zero Hours

S

screechez

Hello,

I am trying to use Task Usage and Resource Usage views to schedule
individual resource assignments during the duration of the task. A task can
have a total duration for many weeks, but resources (people) are typically
used on-and-off during that task. To schedule this, I use task usage to
assign specific hours to people on specific days of the task duration.

The problem is that the work hours between each resource "shift", the task
usage and resource usage view adds 0h (zero hours). I would prefer to see a
blank entry rather than the 0h as it would make it easy to see when resources
are not assigned to do anything. Right now, the work details on my resource
usage is filled up with a lot of 0h's. Is there anyway to get rid of the
zero hours and have them displayed as blanks?

Thank you for your help
 
J

JulieS

Hi Screechez,

Sorry, to the best of my knowledge there is no way of suppressing
the display of the 0h when you stop and start work on an assignment.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 